# Progress & Budgets

> Tracking project progress and budget vs actual

Projects track progress and compare actual time spent against budgeted time. This helps monitor project health and profitability.

## Progress tracking

### Task completion

Progress starts at the task level:

* Each task has a status
* Complete tasks count toward progress
* Simple calculation: completed / total

**Example:**

* 15 tasks in phase
* 10 tasks complete
* Phase progress: 67%

### Phase progress

Each phase calculates its own progress:

* Based on tasks within that phase
* Updates automatically when tasks complete
* Shown as percentage
* Independent of other phases

### Project progress

Overall project progress:

* Weighted average of budgeted phases
* Larger budgets have more impact
* Non-budgeted phases don't contribute
* Shown on project card and detail page

<Info>
  Project progress reflects budgeted work only. Non-budgeted phases track their own progress but don't affect the project total.
</Info>

## Progress calculation

### Weighted average formula

Project with multiple budgeted phases:

**Phase 1 (Design):**

* Budget: 10 days
* Progress: 100% complete
* Contribution: 10 days

**Phase 2 (Development):**

* Budget: 30 days
* Progress: 50% complete
* Contribution: 15 days

**Project total:**

* Combined: 25 days of 40 days
* Progress: 62.5%

### Why weighted?

Weighting ensures:

* Larger phases have proportional impact
* 100% of small phase ≠ 100% of large phase
* Accurate reflection of work completed
* Fair representation of effort

## Budget tracking

### Budget components

Each budgeted phase has:

* **Allocated minutes** - Core work budget
* **QA minutes** - Testing budget
* **Total budget** - Allocated + QA
* **Actual minutes** - Time logged on tasks

### Viewing budget vs actual

Phase detail shows:

* Budgeted time (in days or hours)
* Actual time logged
* Remaining budget
* Over/under budget status

**Example display:**

* Budget: 40 days (18,000 minutes)
* Actual: 35 days (15,750 minutes)
* Remaining: 5 days (2,250 minutes)
* Status: Under budget ✓

### Over budget indicators

When actual exceeds budget:

* Visual indicator (red/warning color)
* Shows overage amount
* Helps catch budget issues early
* PM notified to review

## Time tracking

### Logging time

Time is logged against tasks:

* Each time entry links to a task
* Task belongs to a phase
* Phase aggregates all task time
* Project totals all phase time

### Real-time aggregation

Budget tracking updates automatically:

* Log time on task
* Phase actual minutes increase
* Project totals update
* Progress recalculates

### Historical tracking

All time entries preserved:

* View time logged over project lifecycle
* Compare early vs late phases
* Analyze team member contributions
* Improve future estimates

## Project health indicators

### On track

Project is healthy when:

* Progress matches timeline expectations
* Budget consumption aligns with progress
* No phases significantly over budget
* Completion date achievable

### Warning signs

Watch for:

* Actual time exceeding budget early
* Progress slower than time consumed
* Tasks consistently completing late
* Multiple phases over budget

### Taking action

If project is struggling:

* Review remaining work scope
* Assess if budget increase needed
* Communicate with client
* Adjust resources or timeline

## Monitoring workflows

### PM review cadence

**Daily:**

* Review time entries
* Check for late tasks
* Monitor progress updates

**Weekly:**

* Compare budget vs actual per phase
* Review overall project health
* Identify blockers
* Adjust schedules if needed

**At phase completion:**

* Finalize phase budget analysis
* Document lessons learned
* Apply insights to next phase

### Team member view

Delivery team can see:

* Their assigned tasks
* Task estimates
* Time logged so far
* Cannot see full project budget

<Note>
  Budget details are typically visible to PMs and Managers only. Delivery team focuses on task completion.
</Note>

## Reporting insights

### Budget variance

Compare final vs budgeted:

* Which phases came in under?
* Which phases went over?
* Why? (complexity, scope, unknowns)
* Apply to future estimates

### Task-level analysis

Review completed tasks:

* Estimate vs actual time
* Tasks that took longer
* Tasks that were faster
* Patterns to inform future work

### Efficiency metrics

Measure project efficiency:

* Total budget vs total actual
* Percentage over/under
* Days saved or consumed
* ROI on quoted work

## Best practices

<CardGroup cols={2}>
  <Card title="Log time daily" icon="clock">
    Don't wait until end of week - track as you go
  </Card>

  <Card title="Review budget weekly" icon="calendar">
    Catch issues early before too much overage
  </Card>

  <Card title="Right-size budgets" icon="target">
    Include buffer for unknowns and complexity
  </Card>

  <Card title="Track late reasons" icon="message-square">
    Understand why tasks take longer than planned
  </Card>

  <Card title="Communicate early" icon="megaphone">
    Tell client proactively if budget concerns arise
  </Card>

  <Card title="Learn from each project" icon="graduation-cap">
    Review final numbers to improve future estimates
  </Card>
</CardGroup>

## Common scenarios

### Scenario 1: Phase running over

**Situation:**

* Development phase 60% complete
* 80% of budget consumed
* 40% of work remaining

**Analysis:**

* Will exceed budget
* Estimate 33% overage

**Actions:**

1. Review remaining tasks
2. Identify scope vs estimate issues
3. Communicate with PM and client
4. Consider additional budget or scope reduction

### Scenario 2: Project ahead of schedule

**Situation:**

* 75% of budget used
* 85% of work complete
* Coming in under budget

**Analysis:**

* Efficient execution
* Good estimates
* Potential for early delivery

**Actions:**

1. Maintain quality standards
2. Don't rush final 15%
3. Use extra time for polish
4. Communicate success to client

### Scenario 3: Unbudgeted work requested

**Situation:**

* Client wants additional features
* Not in original scope
* How to track separately?

**Solution:**

1. Create non-budgeted custom phase
2. Add tasks for new work
3. Log time against new phase
4. Track separate from budgeted work
5. Clear delineation for billing

## Understanding the numbers

### Day calculations

Standard conversion:

* 1 day = 450 minutes (7.5 hours)
* Used for consistency
* Matches agency working day
* QA and allocated time use same conversion

### Displaying time

Time shown in most natural unit:

* Over 1 day: shows in days (e.g., "2.5 days")
* Under 1 day: shows in hours (e.g., "6 hours")
* Precise calculations use minutes
* Rounded for display

### Budget precision

Budget set at project creation:

* Specified in whole or half days
* Converted to minutes for tracking
* Prevents accidental changes
* Maintains quote integrity

## Troubleshooting

<AccordionGroup>
  <Accordion title="Progress doesn't match my expectation">
    Project progress is weighted by budget. A small phase completing has less impact than a large phase. Check individual phase progress for details.
  </Accordion>

  <Accordion title="Can't see budget numbers">
    Budget details are visible to PMs and Managers. Delivery team sees task estimates only.
  </Accordion>

  <Accordion title="Time logged doesn't match budget shown">
    Budget is set at project creation. Actual time is sum of all time entries. They should match only when project completes exactly on budget.
  </Accordion>

  <Accordion title="Phase shows over budget">
    This means actual time logged exceeds the allocated + QA budget. Review with PM to determine if additional budget is needed.
  </Accordion>

  <Accordion title="Project progress stuck">
    Progress updates when tasks are marked complete. If tasks are in progress but not completed, progress won't change.
  </Accordion>
</AccordionGroup>

## Next steps

<CardGroup cols={2}>
  <Card title="Projects Overview" icon="folder-kanban" href="/user-guide/projects">
    Back to projects overview
  </Card>

  <Card title="Project Tasks" icon="check-square" href="/user-guide/projects/project-tasks">
    Manage individual tasks
  </Card>

  <Card title="Project Phases" icon="layer-group" href="/user-guide/projects/project-phases">
    Understand phase organization
  </Card>

  <Card title="Time Tracking" icon="clock" href="/user-guide/time-tracking">
    Log time entries
  </Card>
</CardGroup>