Skip to main content
Projects track progress and compare actual time spent against budgeted time. This helps monitor project health and profitability.

Progress tracking

Task completion

Progress starts at the task level:
  • Each task has a status
  • Complete tasks count toward progress
  • Simple calculation: completed / total
Example:
  • 15 tasks in phase
  • 10 tasks complete
  • Phase progress: 67%

Phase progress

Each phase calculates its own progress:
  • Based on tasks within that phase
  • Updates automatically when tasks complete
  • Shown as percentage
  • Independent of other phases

Project progress

Overall project progress:
  • Weighted average of budgeted phases
  • Larger budgets have more impact
  • Non-budgeted phases don’t contribute
  • Shown on project card and detail page
Project progress reflects budgeted work only. Non-budgeted phases track their own progress but don’t affect the project total.

Progress calculation

Weighted average formula

Project with multiple budgeted phases: Phase 1 (Design):
  • Budget: 10 days
  • Progress: 100% complete
  • Contribution: 10 days
Phase 2 (Development):
  • Budget: 30 days
  • Progress: 50% complete
  • Contribution: 15 days
Project total:
  • Combined: 25 days of 40 days
  • Progress: 62.5%

Why weighted?

Weighting ensures:
  • Larger phases have proportional impact
  • 100% of small phase ≠ 100% of large phase
  • Accurate reflection of work completed
  • Fair representation of effort

Budget tracking

Budget components

Each budgeted phase has:
  • Allocated minutes - Core work budget
  • QA minutes - Testing budget
  • Total budget - Allocated + QA
  • Actual minutes - Time logged on tasks

Viewing budget vs actual

Phase detail shows:
  • Budgeted time (in days or hours)
  • Actual time logged
  • Remaining budget
  • Over/under budget status
Example display:
  • Budget: 40 days (18,000 minutes)
  • Actual: 35 days (15,750 minutes)
  • Remaining: 5 days (2,250 minutes)
  • Status: Under budget ✓

Over budget indicators

When actual exceeds budget:
  • Visual indicator (red/warning color)
  • Shows overage amount
  • Helps catch budget issues early
  • PM notified to review

Time tracking

Logging time

Time is logged against tasks:
  • Each time entry links to a task
  • Task belongs to a phase
  • Phase aggregates all task time
  • Project totals all phase time

Real-time aggregation

Budget tracking updates automatically:
  • Log time on task
  • Phase actual minutes increase
  • Project totals update
  • Progress recalculates

Historical tracking

All time entries preserved:
  • View time logged over project lifecycle
  • Compare early vs late phases
  • Analyze team member contributions
  • Improve future estimates

Project health indicators

On track

Project is healthy when:
  • Progress matches timeline expectations
  • Budget consumption aligns with progress
  • No phases significantly over budget
  • Completion date achievable

Warning signs

Watch for:
  • Actual time exceeding budget early
  • Progress slower than time consumed
  • Tasks consistently completing late
  • Multiple phases over budget

Taking action

If project is struggling:
  • Review remaining work scope
  • Assess if budget increase needed
  • Communicate with client
  • Adjust resources or timeline

Monitoring workflows

PM review cadence

Daily:
  • Review time entries
  • Check for late tasks
  • Monitor progress updates
Weekly:
  • Compare budget vs actual per phase
  • Review overall project health
  • Identify blockers
  • Adjust schedules if needed
At phase completion:
  • Finalize phase budget analysis
  • Document lessons learned
  • Apply insights to next phase

Team member view

Delivery team can see:
  • Their assigned tasks
  • Task estimates
  • Time logged so far
  • Cannot see full project budget
Budget details are typically visible to PMs and Managers only. Delivery team focuses on task completion.

Reporting insights

Budget variance

Compare final vs budgeted:
  • Which phases came in under?
  • Which phases went over?
  • Why? (complexity, scope, unknowns)
  • Apply to future estimates

Task-level analysis

Review completed tasks:
  • Estimate vs actual time
  • Tasks that took longer
  • Tasks that were faster
  • Patterns to inform future work

Efficiency metrics

Measure project efficiency:
  • Total budget vs total actual
  • Percentage over/under
  • Days saved or consumed
  • ROI on quoted work

Best practices

Log time daily

Don’t wait until end of week - track as you go

Review budget weekly

Catch issues early before too much overage

Right-size budgets

Include buffer for unknowns and complexity

Track late reasons

Understand why tasks take longer than planned

Communicate early

Tell client proactively if budget concerns arise

Learn from each project

Review final numbers to improve future estimates

Common scenarios

Scenario 1: Phase running over

Situation:
  • Development phase 60% complete
  • 80% of budget consumed
  • 40% of work remaining
Analysis:
  • Will exceed budget
  • Estimate 33% overage
Actions:
  1. Review remaining tasks
  2. Identify scope vs estimate issues
  3. Communicate with PM and client
  4. Consider additional budget or scope reduction

Scenario 2: Project ahead of schedule

Situation:
  • 75% of budget used
  • 85% of work complete
  • Coming in under budget
Analysis:
  • Efficient execution
  • Good estimates
  • Potential for early delivery
Actions:
  1. Maintain quality standards
  2. Don’t rush final 15%
  3. Use extra time for polish
  4. Communicate success to client

Scenario 3: Unbudgeted work requested

Situation:
  • Client wants additional features
  • Not in original scope
  • How to track separately?
Solution:
  1. Create non-budgeted custom phase
  2. Add tasks for new work
  3. Log time against new phase
  4. Track separate from budgeted work
  5. Clear delineation for billing

Understanding the numbers

Day calculations

Standard conversion:
  • 1 day = 450 minutes (7.5 hours)
  • Used for consistency
  • Matches agency working day
  • QA and allocated time use same conversion

Displaying time

Time shown in most natural unit:
  • Over 1 day: shows in days (e.g., “2.5 days”)
  • Under 1 day: shows in hours (e.g., “6 hours”)
  • Precise calculations use minutes
  • Rounded for display

Budget precision

Budget set at project creation:
  • Specified in whole or half days
  • Converted to minutes for tracking
  • Prevents accidental changes
  • Maintains quote integrity

Troubleshooting

Project progress is weighted by budget. A small phase completing has less impact than a large phase. Check individual phase progress for details.
Budget details are visible to PMs and Managers. Delivery team sees task estimates only.
Budget is set at project creation. Actual time is sum of all time entries. They should match only when project completes exactly on budget.
This means actual time logged exceeds the allocated + QA budget. Review with PM to determine if additional budget is needed.
Progress updates when tasks are marked complete. If tasks are in progress but not completed, progress won’t change.

Next steps